Published date: 13 October 2022

Closed opportunity - This means that the contract is currently closed. The buying department may be considering suppliers that have already applied, or no suitable offers were made.


Closing: 20 October 2022, 3:15pm

Contract summary

Industry

  • Street-lighting equipment - 34928500

  • Works for complete or part construction and civil engineering work - 45200000

  • Drainage construction works - 45232450

    • Drainage and surface works - 45232451

    • Drainage works - 45232452

    • Construction, foundation and surface works for highways, roads - 45233000

    • Construction work for highways, roads - 45233100

    • Secondary road construction work - 45233123

    • Road-maintenance works - 45233141

    • Road-repair works - 45233142

    • Installation of road signs - 45233290

    • Installation of road signals - 45233294

    • Installation of road lighting equipment - 45316110

    • Installation of traffic lights - 45316212

Location of contract

North East, West Midlands, London, Yorkshire and the Humber, East Midlands, East of England, North West, South West

Value of contract

£1,000,000 to £2,500,000

Procurement reference

C4N65406483

Published date

13 October 2022

Closing date

20 October 2022

Closing time

3:15pm

Contract start date

28 February 2023

Contract end date

30 September 2025

Contract type

Works

Contract is suitable for SMEs?

Yes

Contract is suitable for VCSEs?

No


Description

Balfour Beatty VINCI (BBV) have been awarded HS2 main works civils contracts, lots N1 and N2 under an Early Contractor Involvement contract (ECI). We are currently in stage two of the process.

We are looking to engage with the supply chain that provides Civil works (site clearance, earthworks, drainage and ducting, kerbs and footways...).
Delta Sublot shall require a sub-contractor to realign and lower the B4114 Birmingham Road between Coleshill and Birmingham, required for the construction of a main asset within the Delta Junction.


Full details and specifications will be provided to the successfully shortlisted suppliers. Suppliers should be aware of the scale of this project and should assess their internal capabilities to be able to carry out the intended scope of work, prior to completing this expression of interest (EOI).


More information

Links


About the buyer

Contact name

Matt Munn

Address

BBV HS2 Offices, 11 Brindley place
Birmingham
B1 2LP
UK

Telephone

07530492643

Email

hs2.procurement@balfourbeattyvinci.com