Published date: 5 February 2021

Closed opportunity - This means that the contract is currently closed. The buying department may be considering suppliers that have already applied, or no suitable offers were made.


Closing: 12 March 2021, 12am

Contract summary

Industry

  • Turbine works - 45315200

Location of contract

North East

Value of contract

£0

Procurement reference

BIP566661393

Published date

5 February 2021

Closing date

12 March 2021

Closing time

12am

Contract start date

1 January 2022

Contract end date

31 December 2036

Contract type

Works

Procedure type

Other: Prior Information

Contract is suitable for SMEs?

No

Contract is suitable for VCSEs?

No


Description

The Combines Heat and Power (CHP) unit within the Energy Centre at University Hospital of Hartlepool (UHH) has been in place since 2004. Its expected life was between 12 and 15 years - this has now been exceeded. Further the engine was scaled against the electrical load of the site in 2003 (circa 1300kW) and it has now dropped to circa 700kW forcing the engine to run sub-optimally.

We are seeking market engagement to develop a specification to meet the needs of the hospital with future proofing technology.


More information

Links


About the buyer

Address

University Hospital of North Tees
Hardwick Road
Stockton-on-Tees
TS19 8PE
England

Telephone

+441642624782

Email

cdda-tr.cardeahelpdesk@nhs.net