Published date: 30 August 2017
This notice was replaced on 29 December 2017
This notice does not contain the most up-to-date information about this procurement. The most recent notice is:
Awarded contract (published 29 December 2017)
Closed opportunity - This means that the contract is currently closed. The buying department may be considering suppliers that have already applied, or no suitable offers were made.
Contract summary
Industry
Demolition, site preparation and clearance work - 45111000
Location of contract
Any region
Value of contract
£0
Procurement reference
Chesterfield Borough Council - CBC/081/17
Published date
30 August 2017
Closing date
10 October 2017
Contract start date
5 February 2018
Contract end date
4 February 2019
Contract type
Works
Procedure type
Open procedure
Any interested supplier may submit a tender in response to an opportunity notice.
Contract is suitable for SMEs?
No
Contract is suitable for VCSEs?
No
Description
Chesterfield Borough Council are seeking contractors for the provision of Demolition of the Multi Storey car park Chesterfield. Saltergate Multi Storey car park is a 10 split-level multi-storey reinforced concrete structure constructed in 1974, it is
adjacent to the Holywell Cross surface car park on the northern edge of Chesterfield Town Centre and is owned and
operated by Chesterfield Borough Council.
This demolition project is to enable the replacement of the Saltergate Multi Storey Car Park as part of the wider mixed
use and public realm regeneration project currently referred to as the Northern Gateway Scheme. The scheme will
consist of asbestos removal and demolition works to make way for the new development.
Full information is contained within the specification and pertaining documents attached on the system.