Published date: 13 May 2025

Open opportunity - This means that the contract is currently active, and the buying department is looking for potential suppliers to fulfil the contract.


Closing: 16 May 2025, 5pm

Contract summary

Industry

  • Concrete pipes and fittings - 44114220

  • Pipelines - 44161000

  • Drainage pipes - 44163110

    • Drainage system - 44163112

    • Sewer pipes - 44163130

    • Ground-drainage work - 45111240

    • Construction work for pipelines, communication and power lines, for highways, roads, airfields and railways; flatwork - 45230000

    • Construction work for pipelines, communication and power lines - 45231000

    • General construction work for pipelines - 45231100

    • Pipelaying construction work - 45231110

    • Installation of pipe system - 45231112

    • Construction work for water and sewage pipelines - 45231300

    • Construction work for sewage pipes - 45232440

    • Drainage construction works - 45232450

    • Drainage and surface works - 45232451

    • Drainage works - 45232452

Location of contract

Any region, North East, London, Yorkshire and the Humber, East of England, North West, South West, West Midlands, East Midlands

Value of contract

£1,000,000 to £2,500,000

Procurement reference

C4N93962725

Published date

13 May 2025

Closing date

16 May 2025

Closing time

5pm

Contract start date

1 September 2025

Contract end date

16 October 2026

Contract type

Service contract

Contract is suitable for SMEs?

Yes

Contract is suitable for VCSEs?

No


Description

A Subcontractor is required to undertake deep drainage within the Saltley Section of Sublot 4. The drainage is approximately 400m in length at 900mm diameter and ranges from 2.5m deep to 7.2m deep, with ground water sitting at approximately 2.5-3.0m deep. The assumption is that some of this pipework would be undertaken using trenchless techniques whilst some of the drainage might be installed traditionally (excavation and ground support). It is also considered that some of the manholes may be sunk rather than excavated with ground support.

The package will be to provide labour, plant and temporary works for the installation of the drainage assets (pipework and manholes) using the methodology determined by the Subcontractor. Permanent works materials will be provided by the Contractor with any temporary materials needed by the Subcontractor to facilitate their works provided by themselves, as well as any sundry items.

It is suggested that a pre-tender meeting is undertaken with interested bidders to ensure that the design that is being developed is in line with their technical requirements for any trenchless operations.


More information

Links

Additional text

Suppliers should be aware of the scale of this project and should assess their internal capabilities to be able to carry out the intended scope of work, prior to completing this expression of interest (EOI).


How to apply

Follow the instructions given in the description or the more information section.


About the buyer

Contact name

Raaquib Khan

Address

BBV HS2 Offices, 11 Brindley place
Birmingham
B1 2LP
UK

Telephone

07405444884

Email

raaquib.khan01@balfourbeattyvinci.com