Published date: 3 July 2018
Awarded contract - This means that the contract has been awarded to a supplier.
Contract summary
Industry
Road junction construction work - 45233125
Location of contract
North West
Value of contract
£0
Procurement reference
GMPTE001-DN291759-13549253
Published date
3 July 2018
Closing date
22 September 2017
Contract start date
4 April 2018
Contract end date
31 March 2022
Contract type
Works
Procedure type
Restricted procedure
A two-stage procedure, where the first stage is used to select suppliers, who are then invited to bid in the second stage.
Contract is suitable for SMEs?
Yes
Contract is suitable for VCSEs?
No
Description
(SCOOT/ MOVA) at various locations throughout the Greater Manchester conurbation. SCOOT is Split Cycle
Offset Optimisation Technique. MOVA is Microprocessor Optimised Vehicle Actuation. To ensure implementation
of adaptive traffic signal control (SCOOT/ MOVA)
- To support this TfGM required two suitably experienced contractors to undertake associated civils enabling
works on a call-off basis, in terms of ducting and other associated minor highways works.
- The SCOOT/MOVA technology itself will then be installed via a separate Traffic Signal Maintenance contract
already in place.
- Following the award of Growth Deal 3 funding it is estimated that this level of funding will enable approximately
60nr junctions to be improved with site works to commence at the start of 2018 and last until the start of 2020.
- Other additional funding may also be obtained during the term of the Framework that results in a requirement
to undertake further works associated with traffic signal junction improvements, these may also be delivered via
the framework.
- The contractual arrangement is also intended to be made available for use by other authorities who may
require works to be delivered via the framework subject to availability of funding. These include the ten
members of the Association of Greater Manchester Authorities.
-There is no guarantee given relating to the value of works to be instructed via this framework agreement.
More information
Links
Award information
Awarded date
3 April 2018
Contract start date
4 April 2018
Contract end date
31 March 2022
Total value of contract
£0
This contract was awarded to 2 suppliers.
J Cooney Ltd
Address
J. Cooney Ltd, Albion Road, Rochdale, OL11 4HQ
Reference
None
Supplier is SME?
Yes
Supplier is VCSE?
No
Rosgal Ltd
Address
ROSGAL LTD, CBA HOUSE, SANDFOLD LANE, MANCHESTER M19 3BJ
Reference
None
Supplier is SME?
Yes
Supplier is VCSE?
No
About the buyer
Contact name
Matthew Robinson
Address
TfGM
2,Piccadilly Place,
Manchester
M1 3BG
United Kingdom
Telephone
+44 1612551125
Website
Share this notice
Closing: 22 September 2017