Published date: 21 October 2022

Closed opportunity - This means that the contract is currently closed. The buying department may be considering suppliers that have already applied, or no suitable offers were made.


Closing: 25 November 2022, 12pm

Contract summary

Industry

  • Construction work for multi-dwelling buildings and individual houses - 45211000

Location of contract

England

Value of contract

£3,500,000 to £4,500,000

Procurement reference

TAUNTD001-DN638595-08129279

Published date

21 October 2022

Closing date

25 November 2022

Closing time

12pm

Contract start date

20 December 2022

Contract end date

19 December 2025

Contract type

Works

Procedure type

Open procedure

Any interested supplier may submit a tender in response to an opportunity notice.

Contract is suitable for SMEs?

Yes

Contract is suitable for VCSEs?

Yes


Description

The Council is looking to appoint to two Lots. Bidders may bid for one or both Lots separately.

Lot 1 Refurbishment of Woolaway Houses North Taunton - Phase E

The Works comprise the complete refurbishment of the properties on the basis that all the
external walls, windows and doors are replaced; all roofing is stripped and re-laid; and a full
package of internal replacement and upgrading is provided all as shown and described on
the tender and contract drawings and the specifications.
The Works will be executed in Sections using the following parameters:

Section 1: Works to 4 Bodmin Road; 9, 25 & 27 Dorchester Road Date of Possession to be 4
calendar weeks after the signing of the JCT Contract. The Date for Completion to be 20
calendar weeks after the Date of Possession.
Section 2: Works to 17, 23, 33 & 35 Dorchester Road Date of Possession to be 2 weeks after
the completion of Section 1. The Date for Completion to be 16 calendar weeks after the Date
of Possession.

Lot 2 Refurbishment of Woolaway Houses Oake

The Works comprise the complete refurbishment of the properties on the basis that all the
external walls, windows and doors are replaced; all roofing is stripped and re-laid; and a full
package of internal replacement and upgrading is provided all as shown and described on
the tender and contract drawings and the specifications.
The Works will be executed in Sections using the following parameters:
Section 1: Works to 21, 23 and 24 Oake Close Date of Possession to be 4 calendar weeks
after the signing of the JCT Contract. The Date for Completion to be 20 calendar weeks after
the Date of Possession.
Section 2: Works to 17, 18 and 19 Oake Close Date of Possession to be 2 weeks after the
completion of Section 1. The Date for Completion to be 16 calendar weeks after the Date of
Possession.
Section 3: Works to 2, 3 and 4 Oake Close Date of Possession to be 2 weeks after the
completion of Section 2. The Date for Completion to be 16 calendar weeks after the Date of
Possession.
Section 4: Works to 25 Oake Close Date of Possession to be 2 weeks after the completion of
Section 3. The Date for Completion to be 16 calendar weeks after the Date of Possession.


About the buyer

Contact name

Michael OHalloran

Address

The Deane House
Belvedere Road
Taunton
TA1 1HE
England

Telephone

+44 7773197467

Email

m.ohalloran@somersetwestandtaunton.gov.uk

Website

https://www.somersetwestandtaunton.gov.uk