Published date: 25 March 2021
Awarded contract - This means that the contract has been awarded to a supplier.
Contract summary
Industry
Construction work - 45000000
Location of contract
England
Value of contract
£28,000
Procurement reference
CUM001-DN534877-14622201
Published date
25 March 2021
Closing date
1 March 2021
Closing time
12pm
Contract start date
29 March 2021
Contract end date
30 October 2021
Contract type
Works
Procedure type
Other
Contract is suitable for SMEs?
Yes
Contract is suitable for VCSEs?
No
Description
Butterburn bridge carries the U1241 road over the Butter Burn (not a main river). The bridge lies approximately 10km to the east of the village of Bewcastle. It is a single span structure comprising of rolled steel joints encased in concrete. Works to this asset were undertaken in 2018. Details of which can be reviewed in the attached Completion Report, titled 'MET-1232-CA184-ST-REP-00001_iss1_rev0'.
The bridge requires repair of the gabion baskets which are reported to have collapsed and washed out. Therefore, these require replacement, remove stone from both layers of existing gabion baskets, place new gabion baskets on same foundation and refil using reclaimed stone from existing baskets. Back fill voids behind new baskets with no fines concrete.
Award information
Awarded date
25 March 2021
Contract start date
29 March 2021
Contract end date
31 October 2021
Total value of contract
£28,207.98
This contract was awarded to 1 supplier.
Metcalfe Plant Hire
Address
Penrith
Reference
None
Supplier is SME?
No
Supplier is VCSE?
No
About the buyer
Contact name
Hayley Samson
Address
Cumbria House
107 - 117 Botchergate
Carlisle
CA1 1RD
United Kingdom
Telephone
+44 1228226417
Website
Share this notice