Published date: 16 February 2023

Awarded contract - This means that the contract has been awarded to a supplier.


Closing: 27 January 2023, 2pm

Contract summary

Industry

  • Surface dressing - 44113810

  • Various surface works - 45233200

  • Surface work for highways - 45233210

    • Surface work for roads - 45233220

    • Paving and asphalting works - 45233222

    • Carriageway resurfacing works - 45233223

    • Surface coating construction work - 45233228

    • Resurfacing works - 45233251

    • Surface work for footpaths - 45233253

Location of contract

England

Value of contract

£650,000

Procurement reference

DORST001-DN648737-02719880

Published date

16 February 2023

Closing date

27 January 2023

Closing time

2pm

Contract start date

1 May 2023

Contract end date

31 October 2023

Contract type

Supply contract

Procedure type

Restricted procedure

A two-stage procedure, where the first stage is used to select suppliers, who are then invited to bid in the second stage.

Contract is suitable for SMEs?

No

Contract is suitable for VCSEs?

No


Description

Dorset Highways is looking to appoint a Principal Contractor to carry out In situ recycling and subsequent surfacing to a number of areas as listed within the county of Dorset.

Work included within this call off are:
• Establishing and providing suitable and sufficient welfare facilities in accordance with the Construction (Design and Management) Regulations 2015 (SI 2015/51).
• Traffic management in accordance with Chapter 8 of the Traffic Signs Manual; to be approved -by Dorset Highways prior to establishment. Road closures, gate personnel and signed diversions. Road closures are subject to programme and application timings for these and all road closure applications must be submitted to, and approved by, the Dorset Highways Traffic Team.
• The works are as described and detailed within Contract Specific Sub Specification B (in conjunction with Contract Specific Sub Specification C)
• Adjustment to any required ironworks/service covers prior to road opening.
• Stakeholder engagement methods to be discussed and agreed with Dorset Traffic team prior to implementation.
• Replacement of all existing road markings. Any and all nominated sub contractors to be agreed with Dorset Highways.

This is a call-off from the Road Surface Treatments DPS


Award information

Awarded date

13 February 2023

Contract start date

1 May 2023

Contract end date

31 October 2023

Total value of contract

£674,393.49

This contract was awarded to 1 supplier.

Stabilised Pavements Limited

Address

Ironstone House Scaldwell Northants NN6 9JS

Reference

None

Supplier is SME?

Yes

Supplier is VCSE?

No


About the buyer

Contact name

Alice Crocker

Address

Dorset Council
County Hall, Colliton Park
Dorchester
DT1 1XJ
England

Telephone

+44 1305221719

Email

alice.crocker@dorsetcouncil.gov.uk

Website

https://www.dorsetcouncil.gov.uk