Published date: 21 February 2024

Closed opportunity - This means that the contract is currently closed. The buying department may be considering suppliers that have already applied, or no suitable offers were made.


Closing: 28 February 2024, 5:11pm

Contract summary

Industry

  • Building construction work - 45210000

  • Construction work for commercial buildings, warehouses and industrial buildings, buildings relating to transport - 45213000

  • Construction work for warehouses and industrial buildings - 45213200

    • Construction work for industrial buildings - 45213250

    • Buildings associated with transport - 45213300

    • Construction work for buildings relating to railway transport - 45213320

    • Construction work for buildings relating to various means of transport - 45213350

    • Electrical installation work of heating and other electrical building-equipment - 45315000

    • Mechanical engineering installation works - 45351000

    • Installation services of electrical and mechanical equipment - 51100000

    • Installation services of mechanical equipment - 51120000

    • Mechanical engineering services - 71333000

    • Mechanical and electrical engineering services - 71334000

Location of contract

East Midlands, West Midlands, South East

Value of contract

£20,000,000 to £30,000,000

Procurement reference

C4N77930432

Published date

21 February 2024

Closing date

28 February 2024

Closing time

5:11pm

Contract start date

14 July 2024

Contract end date

31 August 2025

Contract type

Works

Contract is suitable for SMEs?

No

Contract is suitable for VCSEs?

No


Description

EKFB are delivering civil engineering works across an 80km section of the new high speed rail link between the Chiltern Tunnel and Long Itchington Wood. Our scope of the works includes 15 viaducts, 6.9km of green tunnels, 22km of road diversions, 81 bridges and around 30 million cubic metres of excavation.

EKFB are seeking to appoint a sub-contractor undertake the construction of 4 green tunnel portal building as detailed below:
The buildings are to accommodate the mechanical, electrical, and communication equipment for operation of the tunnel. There will be a total of four portal buildings which are expected to have identical specifications and dimensions. Each building will be 50m length and a 15m width. See general arrangement.
The buildings are situated at each end of the tunnels, which are located at Chipping Warden & Greatworth.
Ground works and concrete slab will be carried out by EKFB, so this package is for all works above concrete slab and include but not limited to:
• Steelwork
• Cladding & Roofing
• Internal fit out - ie. blockwork, partitions, plastering, painting, fire stopping, joinery
• Mechanical & Electrical works ie, natural ventilation system , general mechanical heat recovery ventilation system, temperature control ventilation system, mechanical cooling system, electrical heating system, building management system, automatic monitoring & control, fire detection & alarm, fire hydrant system ,uninterrupted power system, cable management system, gas suppression system, normal & emergency lighting, power supply system, distribution for lighting, small power, emergency lighting, mechanical cooling and heating system, distribution for communication and other essential services
• Landscaping Work


More information

Links


About the buyer

Contact name

Chris Read

Address

Floor 5, 19 Cornwall Street
Birmingham
B3 2DT
UK

Telephone

07792825436

Email

supplychainenquiries@ekfb.com