Contract summary
Industry
Electrical equipment and apparatus - 31600000
Location of contract
Yorkshire and the Humber
Value of contract
£250,000 to £300,000
Procurement reference
2992
Published date
25 October 2019
Closing date
13 December 2019
Contract start date
1 April 2020
Contract end date
31 March 2025
Contract type
Supply contract
Procedure type
Competitive dialogue (above threshold)
Tenders are invited from pre-qualified suppliers after discussion of requirements and potential solutions.
This procedure can be used for procurements above the relevant contract value threshold.
Contract is suitable for SMEs?
Yes
Contract is suitable for VCSEs?
No
Description
South Yorkshire Passenger Transport Executive (SYPTE) owns the Supertram infrastructure. South Yorkshire Supertram Ltd (SYSL) commenced operation in 1994 and SYPTE let a Concession to Stagecoach through SYSL to operate and maintain the Supertram system on its behalf in 1997. This Concession expires in 2024.
As part of the Sheffield City Council (SCC) Streets Ahead PFI Amey as SCC's contractor has a contractual responsibility to replace all the traffic signals across the city. A number of these traffic signals interface with South Yorkshire Supertram.
The road traffic controllers at sites where there is an interface with South Yorkshire Supertram are being replaced with a modern unit (telent Optima LRT Mode) and the voltage of the road traffic signals is being reduced to a low voltage level of 48Vac.
Replacement of the road traffic signal heads is the responsibility of Amey, SYPTE are however required to supply the Tram Signal Head and associated bracketry to allow its installation on a road traffic signal pole and is ready to be mounted on the traffic signal furniture. This work commenced in 2018 and is due to end in 2024. A total of 63 sites still to be replaced
• 2020 - 13 sites (60 units)
• 2021 - 16 sites (48 units)
• 2022 - 15 sites (35 units)
• 2023 - 12 sites (58 units)
• 2024 - 7 sites (40 units)
The above is the current estimated requirement.
SYPTE therefore requires a supplier of replacement ELV compatible LED Tram signal heads for the Supertram network.
More information
Additional text
-
Full documentation can be downloaded from http://www.sypte.co.uk/WhatWeDo/Contracts
About the buyer
Address
11 Broad Street West
SHEFFIELD