Contract summary
Industry
Surface work for highways - 45233210
Location of contract
Any region
Value of contract
£261,600,000
Procurement reference
tender_237180/931600
Published date
8 March 2021
Closing date
29 September 2020
Closing time
3pm
Contract start date
29 April 2021
Contract end date
31 March 2025
Contract type
Works
Procedure type
Restricted procedure (above threshold)
A two-stage procedure, where the first stage is used to select suppliers, who are then invited to bid in the second stage.
This procedure can be used for procurements above the relevant contract value threshold.
Contract is suitable for SMEs?
No
Contract is suitable for VCSEs?
No
Description
Design and build arrangement demolishing existing pavement, replacing with new (flexible or composite) and
overlaying of concrete pavements.
The works in scope are:
- demolition of existing concrete pavements,
- construction of new pavement (which could be flexible or composite),
- overlay of existing concrete pavements,
- changes to or replacement of associated assets such as sub-surface drainage.
The reconstruction works contractors will be expected to provide:
- principal designer duties,
- optioneering of solutions,
- detailed solution design,
- public consultation,
- early contractor involvement into initial design phase,
- construction,
- demolition,
- principal contractor duties,
- traffic management,
- welfare facilities.
Provides contingency should the other framework supplier be unable to deliver the works.
More information
Previous notice about this procurement
Concrete Roads Programme - Reconstruction Framework
- Future opportunity
- Published 16 April 2020
About the buyer
Address
Highways England, Woodlands, Manton Lane
Bedford
MK41 7LW
England
Share this notice
Closing: 29 September 2020, 3pm